O₂

Power planner

Generator output, circuit demand, wire capacity and battery reserves.

Circuit buildings

Building 1

Consumes

Water1 kg/s

Produces

Hydrogen Gas0.112 kg/s

Oxygen0.888 kg/s

120 W consumed

Building 2

Consumes

Hydrogen Gas0.1 kg/s

800 W generated

Active time is your planned operating time. Inputs must be supplied continuously while a building runs.

Wiring

Wire
Heavi-Watt Wire120 / 20,000 W

Within wire capacity

Peak demand assumes all enabled consumers run together. Average operating time does not reduce the wire capacity they need.

Battery bank

Battery

Battery · 10 / 10 kJ

Power balance

Average generation

800

W

Average demand

120

W

Net power

+680

W

Peak demand

120

W

Energy generated per cycle
480 kJ
Energy consumed per cycle
72 kJ

Battery times use stored energy and the average power balance. Leakage, start-up peaks and generator control are not included.

Colony resources

Carry these buildings and operating times into the oxygen, water and food balance.

Open colony plan